The caissons on the North ramp are being drilled. General Construction bids for the entrance canopy have been received and are in the review process. Passenger Security Checkpoint construction activity is on schedule to begin Fall 2017.

Parking Update All parking lots remain open. The new ROC Airport Smart Phone Lot is open and operating. 

Traffic Pattern Updates None. Traffic patterns remain the same.

Terminal/Security/Gate Update Construction has commenced to relocate the Hudson News Store for the baggage claim passenger waiting area on the lower level of the terminal. Restroom renovations continue post-security. Electrical connectivity for the air conditioning control system is progressing. There are no construction-related changes in ticketing or security at this time.

Bid opportunities currently available for the project can be reviewed at the Monroe County Purchasing website.

Be sure to follow the progress at RocRenovation.com and on social media! We’re on Facebook (facebook.com/ROCAirport) and Twitter (@ROCAirport).

 

Photo Right: Caisson drilling on the North Ramp.

Photo Left: Relocation of Hudson News Store.

 

 

 

For General Airport News Visit rocairport.com