Seneca Park Zoo Tropics Project Updates

Adult and Child approach new front entry plaza (rendering)Last Update: October 21, 2022

Introduction

Monroe County is currently undertaking a multimillion dollar project at Seneca Park Zoo that will restore the heart of the facility, replacing the former Main Building with the largest indoor tropics complex of its kind and a 220,000-gallon aquarium, along with new guest services, ticketing, and conference areas.  This page has been created to share updates, information and renderings with the public as the project progresses.

Current Status

Enabling Phase: October 2022 thru Spring 2023

Relocation of utilities, burial of overhead power and communication lines, construction of east service road installation of new 12 foot wood stockade secondary containment fence, and reconstruction of abandoned CSX right of way into 6 foot wide stone dust trail.

Early commencement of tree removals along the existing chain link fence and trail started the week of October 17th.  Contractor has been setting up temporary construction fencing for future deliveries and construction staging.

Next week will bring further site clearing and installation of stormwater protection measures.

Tentative Schedule of Upcoming Activities

(Please note some activities’ dates overlap)

Oct. 17-28 Clearing and Grubbing
Oct. 19-21 Removal of sections of wooden stockade fence
Oct. 27-28 Install silt fence and drainage inlet protection
Oct. 31-Nov. 9 Earthwork
Nov. 7-11 Sanitary sewer installation
Nov. 7-11 Forcemain installation

Rendering of new Tropics Complex at Seneca Park Zoo